Power plant supply
Power plant supply
Construction time
10 Months
Order volume
1.200.000 €
Project objective
- Central tank farm with filling station to supply the gas engines in the power plant
- Media: Urea solution, lubricating oil and heating oil (filling lines caustic soda, hydrochloric acid)
- Complete 3D planning
- Piping, pump technology, fittings, measurement technology
- Complete electrical engineering incl. Visualization
Special features
- Vertical, double-walled storage containers (heated) with bottom outlet
- Discharge area with sump fully coated (against acids, alkalis and oils)
- Double-walled plastic pipes for caustic soda and hydrochloric acid
- Redundant 24/7 operation of the urea supply